Pursuant to Senate Bill 20 passed during the 84th Texas Legislative Session, this information is made available to comply with the requirements for transparency in state agency contracting and procurement set forth in the bill.
VENDOR NAME![]() |
TFC CONTRACT #![]() |
AMOUNT![]() |
CONTRACT TYPE![]() |
DETAILS![]() |
|---|---|---|---|---|
| Flynn Construction, Inc. | 22-174-000 | $4,033,440.00 | Construction Manager at Risk | VIEW + |
| Flynn Construction Inc. | 22-174-000 | $0.00 | CMR GMP Amendment 1 | VIEW + |
| Flynn Construction Inc | 22-174-000 | $0.00 | Amendment 2 | VIEW + |
| Flynn Construction Inc | 22-174-000 | $627,473.55 | CMR GMP Amendment 2 | VIEW + |
| Flynn Construction Inc | 22-174-000 | $0.00 | Amendment 3 | VIEW + |
| Flynn Construction Inc | 22-174-000 | $300,000.00 | Amendment 4 | VIEW + |
| Broaddus and Associates Inc | 22-173-000 | $564,030.00 | Amendment 5 | VIEW + |
| Broaddus and Associates Inc | 22-173-000 | $489,395.00 | Amendment 4 | VIEW + |
| Broaddus and Associates Inc | 22-173-000 | $247,500.00 | Amendment 3 | VIEW + |
| Broaddus & Associates Inc | 22-173-000 | $0.00 | Amendment 1 | VIEW + |
| Broaddus & Associates Inc | 22-173-000 | $0.00 | Amendment 2 | VIEW + |
| Broaddus & Associates Inc | 22-173-000 | $1,836,914.00 | Program Management Professional | VIEW + |
| Chargepoint Inc | 22-169-000 | $0.00 | Master Services and Subscription Agreement | VIEW + |
| The Gordian Group Inc | 22-167-000 | $100,000.00 | Job Order Contracting Services | VIEW + |
| The Gordian Group Inc | 22-167-000 | $0.00 | Amendment 1 | VIEW + |
| The Gordian Group Inc | 22-167-000 | $500,000.00 | Amendment 2 | VIEW + |
| The Gordian Group Inc | 22-167-000 | $2,000,000.00 | Amendment No. 4 | VIEW + |
| The Gordian Group, Inc | 22-167-000 | $1,000,000.00 | Amendment 3 | VIEW + |
| R. L. Townsend & Associates, LLC | 22-166-000 | $100,000.00 | Amendment 2 | VIEW + |
| RL Townsend | 22-166-000 | $100,000.00 | Amendment 3 | VIEW + |
| R L Townsend & Associates LLC | 22-166-000 | $100,000.00 | Amendment 1 | VIEW + |
| R L Townsend & Associates LLC | 22-166-000 | $100,000.00 | Professional Services | VIEW + |
| DH Pace Company Inc | 22-164-000 | $500,000.00 | Service Contract | VIEW + |
| D H Pace Company Inc | 22-164-000 | $800,000.00 | Amendment 1 | VIEW + |
| D H Pace Company Inc | 22-164-000 | $0.00 | Amendment 2 | VIEW + |
| Tom Green and Company Engineers Inc | 22-156-000 | $1,000,000.00 | Amendment 3 | VIEW + |
| Tom Green and Company Engineers Inc | 22-156-000 | $2,530,000.00 | Amendment 2 | VIEW + |
| Tom Green and Company Engineers Inc | 22-156-000 | $4,000,000.00 | Amendment 1 | VIEW + |
| Tom Green and Company Engineers Inc | 22-156-000 | $9,900,000.00 | Professional Services | VIEW + |
| Northern Lights Group dba Spaulding Decon | 22-155-000 | $500,000.00 | Service Contract | VIEW + |
| Marmon Mok LLP | 22-153-000 | $4,948,782.00 | Professional Services | VIEW + |
| Marmon Mok, LP | 22-153-000 | $3,007,861.65 | Amendment 1 | VIEW + |
| Marmon Mok LLP | 22-153-000 | $96,267.60 | Amendment No. 2 | VIEW + |
| Fischer Management Services Inc | 22-152-000 | $176,317.56 | Amendment 1 | VIEW + |
| Fischer Management Services Inc | 22-152-000 | $129,511.00 | Software Maintenance Services | VIEW + |
| Koetter Fire Protection of Austin LLC | 22-146-000 | $300,045.00 | Amendment 2 | VIEW + |
| Koetter Fire Protection of Austin LLC | 22-146-000 | $200,000.00 | Amendment 1 | VIEW + |
| Koetter Fire Protection of Austin LLC | 22-146-000 | $300,045.00 | Service Contract | VIEW + |
| Koetter Fire Protection of Austin LLC | 22-146-000 | $0.00 | Amendment 3 | VIEW + |
| Koetter Fire Protection of Austin LLC | 22-146-000 | ($2,970.00) | Amendment 4 | VIEW + |
| Koetter Fire Protection of Austin LLC | 22-146-000 | $35,000.00 | Amendment No. 6 | VIEW + |
| Koetter Fire Protection of Austin LLC | 22-146-000 | $100,445.00 | Amendment 5 | VIEW + |
| Stanely Consultants Inc | 22-145-000 | $0.00 | Amendment 1 | VIEW + |
| Stanley Consultants Inc | 22-145-000 | $372,760.00 | Professional Services | VIEW + |
| Energy Engineering Associates Inc dba EEA Consulting Engineers | 22-144-000 | $154,810.00 | Professional Services | VIEW + |
| Energy Engineering Associates Inc dba EEA Consulting Engineers | 22-144-000 | $0.00 | Amendment 1 | VIEW + |
| Square One Consultants Inc | 22-142-000 | $1,836,080.00 | Amendment 2 | VIEW + |
| Square One Consultants Inc | 22-142-000 | $333,100.00 | Amendment 1 | VIEW + |
| Square One Consultants Inc | 22-142-000 | $4,392,745.00 | Project Management Professional Capitol Complex Phase Two | VIEW + |
| iOffice LP | 22-140-000 | $0.00 | Confidentiality Agreement | VIEW + |
| Belfor USA Group Inc | 22-136-000 | $8,000,000.00 | Water, Fire, and Biohazard Remediation Services | VIEW + |
| Belfor USA Group Inc | 22-136-000 | $800,000.00 | Amendment 1 | VIEW + |
| Walter P Moore & Associates Inc | 22-134-000 | $17,500.00 | Professional Services | VIEW + |
| Construction Managers of Southeast Texas LLC | 22-133-000 | $174,198.44 | Amendment 1 | VIEW + |
| Construction Managers of Southeast Texas LLC | 22-133-000 | $362,070.00 | Guaranteed Maximum Price Amendment 2 | VIEW + |
| Construction Manager of Southeast Texas LLC | 22-133-000 | $0.00 | Amendment 3 | VIEW + |
| Construction Manager of Southeast Texas LLC | 22-133-000 | $706,927.30 | Construction Manager At Risk | VIEW + |
| Central Texas Refuse LLC | 22-132-000 | $264,725.89 | Service | VIEW + |
| Central Texas Refuse LLC | 22-132-000 | $252,847.68 | Amendment 1 | VIEW + |
| Central Texas Refuse LLC | 22-132-000 | ($12,880.61) | Amendment 2 | VIEW + |
| Turner Construction Company | 22-131-000 | $0.00 | Guaranteed Maximum Price Amendment 1 | VIEW + |
| Turner Construction Company | 22-131-000 | $130,150,000.00 | Construction Manager at Risk | VIEW + |
| J E Dunn Construction Company | 22-130-000 | $51,052,467.00 | Construction Manager at Risk | VIEW + |
| J E Dunn Construction Company | 22-130-000 | $201,947,533.00 | Amendment 2 | VIEW + |
| J E Dunn Construction Company | 22-130-000 | $0.00 | Amendment 1 | VIEW + |
| JE Dunn Construction Company | 22-130-000 | $4,500,000.00 | Amendment 3 | VIEW + |
| JE Dunn Construction Company | 22-130-000 | $0.00 | GMP Amendment 1 | VIEW + |
| J E Dunn Construction Company | 22-130-000 | $203,864,649.00 | Amendment 4 | VIEW + |
| J E Dunn Construction Company | 22-130-000 | $10,000,000.00 | Amendment No. 1 to GMP No.1 | VIEW + |
| Hellmuth, Obata & Kassabaum Inc | 22-129-000 | $568,300.86 | Amendment 2 | VIEW + |
| Hellmuth, Obata & Kassabaum Inc | 22-129-000 | $1,377,970.63 | Amendment 3 | VIEW + |
| Hellmuth, Obata & Kassabaum Inc | 22-129-000 | $1,102,677.00 | Amendment 4 | VIEW + |
| Hellmuth Obata & Kassabaum Inc | 22-129-000 | $505,625.00 | Amendment 1 | VIEW + |
| Hellmuth Obata & Kassabaum Inc | 22-129-000 | $19,600,000.00 | Professional Services | VIEW + |
| Huitt Zollars Inc | 22-124-000 | $0.00 | Amendment 1 | VIEW + |
| Huitt Zollars Inc | 22-124-000 | $24,280.00 | Professional Services | VIEW + |
| Perkins & Will Inc | 22-123-000 | $8,665,629.00 | Professional Services | VIEW + |
| SI Mechanical LLC | 22-122-000 | $400,000.00 | Service HVAC | VIEW + |
| Si Mechanical LLC | 22-122-000 | $300,000.00 | Amendment 3 | VIEW + |
| SI Mechanical LLC | 22-122-000 | $200,000.00 | Amendment 2 | VIEW + |
| SI Mechanical LLC | 22-122-000 | $400,000.00 | Amendment 1 | VIEW + |
| Dynamic Systems Inc | 22-121-000 | $400,000.00 | Amendment 1 | VIEW + |
| Dynamic Systems Inc | 22-121-000 | $200,000.00 | Amendment 2 | VIEW + |
| Dynamic Systems Inc | 22-121-000 | $700,000.00 | Amendment 3 | VIEW + |
| Dynamic Systems Inc | 22-121-000 | $400,000.00 | Service | VIEW + |
| Entech Sales & Services LLC | 22-120-000 | $800,000.00 | Service HVAC | VIEW + |
| Cool Services Inc | 22-119-000 | $800,000.00 | Service | VIEW + |
| Cool Services Inc | 22-119-000 | $300,000.00 | Amendment 2 | VIEW + |
| Cool Services Inc | 22-119-000 | $800,000.00 | Amendment 1 | VIEW + |
| BEARD INTERGRATED SYSTEMS INC | 22-118-000 | $8,000,000.00 | SERVICE | VIEW + |
| Mechanical & Process Systems LLC | 22-117-000 | $800,000.00 | Service | VIEW + |
| Mechanical and Process Systems LLC | 22-117-000 | $800,000.00 | Amendment 1 Renewal | VIEW + |
| Mechanical and Process Systems LLC | 22-117-000 | $0.00 | Correction No. 1 to Amendment No. 1 | VIEW + |
| Mechanical and Process Systems LLC | 22-117-000 | $300,000.00 | Amendment 2 | VIEW + |
| J T Vaughn Construction | 22-116-000 | $0.00 | Amendment 2 | VIEW + |
| J T Vaughn Construction LLC | 22-116-000 | $2,000,000.00 | Construction Manager at Risk | VIEW + |
| J T Vaughn Construction LLC | 22-116-000 | $0.00 | Guaranteed Maximum Price Amendment 1 | VIEW + |
| J T Vaughn Construction LLC | 22-116-000 | $1,000,000.00 | Amendment 1 | VIEW + |
| AK Telecom LLC | 22-115-000 | $400,000.00 | Amendment 1 | VIEW + |
| AK Telecom LLC | 22-115-000 | $200,000.00 | Service | VIEW + |
| AK Telecom LLC | 22-115-000 | $0.00 | Amendment 4 | VIEW + |
| AK Telecom LLC | 22-115-000 | $0.00 | Amendment 3 | VIEW + |
| AK Telecom LLC | 22-115-000 | $100,000.00 | Amendment 2 | VIEW + |
| Elite Entrances, LLC | 22-114-000 | $100,000.00 | Amendment 2 | VIEW + |
| Elite Enterprises LLC | 22-114-000 | $300,000.00 | Service | VIEW + |
| Elite Entrances LLC | 22-114-000 | $500,000.00 | Amendment 1 | VIEW + |
| Posillico Civil Inc | 22-112-000 | $0.00 | Amendment 5 | VIEW + |
| Posillico Civil Inc | 22-112-000 | $0.00 | Amendment 4 | VIEW + |
| Posillico Civil Inc | 22-112-000 | $0.00 | Amendment 3 | VIEW + |
| Posillico Civil Inc | 22-112-000 | $0.00 | Amendment 2 | VIEW + |
| Posillico Civil Inc | 22-112-000 | $161,270,000.00 | Amendment 1 | VIEW + |
| Posillico Civil Inc | 22-112-000 | $995,000.00 | Construction - Design Build | VIEW + |
| Posillico Civil Inc | 22-112-000 | ($94,716.22) | Amendment 21 | VIEW + |
| Posillico Civil Inc | 22-112-000 | $2,327,923.78 | Amendment 20 | VIEW + |
| Posillico Civil Inc | 22-112-000 | $0.00 | Amendment 19 | VIEW + |
| Posillico Civil Inc | 22-112-000 | $0.00 | Amendment 17 | VIEW + |
| Posillico Civil Inc | 22-112-000 | $5,000,000.00 | Amendment 18 | VIEW + |
| Posillico Civil Inc | 22-112-000 | $0.00 | Amendment 10 | VIEW + |
| Posillico Civil Inc | 22-112-000 | $0.00 | Amendment 9 | VIEW + |
| Posillico Civil Inc | 22-112-000 | $0.00 | Amendment 7 | VIEW + |
| Posillico Civil Inc | 22-112-000 | $185,000,000.00 | Amendment 8 | VIEW + |
| Posillico Civil Inc | 22-112-000 | $0.00 | Amendment 6 | VIEW + |
| Posillico Civil Inc | 22-112-000 | $0.00 | Amendment 13 | VIEW + |
| Posillico Civil Inc | 22-112-000 | $0.00 | Amendment 12 | VIEW + |
| Posillico Civil Inc | 22-112-000 | $0.00 | Amendment 11 | VIEW + |
| Posillico Civil, Inc | 22-112-000 | $0.00 | Amendment 16 | VIEW + |
| Posillico Civil Inc | 22-112-000 | $0.00 | Amendment 14 | VIEW + |
| Posillico Civil Inc | 22-112-000 | $0.00 | Amendment 15 | VIEW + |
| Doucet & Associates Inc | 22-111-000 | $250,000.00 | Amendment 1 | VIEW + |
| Doucet & Associates Inc | 22-111-000 | $250,000.00 | IDIQ Civil Engineering and Land Utility Survey | VIEW + |
| Bain Medina Bain Inc | 22-110-000 | $250,000.00 | IDIQ Civil Engineering and Land Utility Survey | VIEW + |
| Bain Medina Bain Inc | 22-110-000 | $250,000.00 | Amendment 1 | VIEW + |
| KCI Technologies Inc | 22-109-000 | $250,000.00 | Amendment 1 | VIEW + |
| KCI Technologies Inc | 22-109-000 | $250,000.00 | IDIQ Civil Engineering and Land Utility Survey | VIEW + |
| KCI Technologies Inc | 22-109-000 | $9,655.83 | Assignment 1 | VIEW + |
| Nicole Francois Consulting Inc dba CONVEYANCE Civil Engineering | 22-108-000 | $250,000.00 | IDIQ Civil Engineering and Land Utility Survey | VIEW + |
| Halff Associates Inc | 22-107-000 | $250,000.00 | IDIQ Civil Engineering and Land Utility Survey | VIEW + |
| Halff Associates Inc | 22-107-000 | $250,000.00 | Amendment 1 | VIEW + |
| Halff Associates Inc | 22-107-000 | $5,700.00 | Assignment 1 | VIEW + |
| Halff Associates Inc | 22-107-000 | $30,071.00 | Assignment 2 | VIEW + |
| Parkhill, Smith & Cooper Inc dba Parkhill | 22-106-000 | $0.00 | Amendment No. 1 to Assignment No. 3 | VIEW + |
| Parkhill Smith & Cooper Inc dba Parkhill | 22-106-000 | $76,850.00 | Assignment 4 | VIEW + |
| Parkhill Smith & Cooper Inc dba Parkhill | 22-106-000 | $125,000.00 | Assignment 3 | VIEW + |
| Parkhill Smith & Cooper Inc dba Parkhill | 22-106-000 | $250,000.00 | Amendment 1 | VIEW + |
| Parkhill Smith & Cooper Inc DBA Parkhill | 22-106-000 | $250,000.00 | IDIQ Civil Engineering and Land Utility Survey | VIEW + |
| Parkhill Smith & Cooper Inc dba Parkhill | 22-106-000 | $0.00 | Amendment 1 to Assignment 1 | VIEW + |
| Parkhill Smith & Cooper Inc dba Parkhill | 22-106-000 | $16,500.00 | Assignment 1 | VIEW + |
| Parkhill Smith & Cooper Inc dba Parkhill | 22-106-000 | $31,250.00 | Assignment 2 | VIEW + |
| MWM Design Group Inc | 22-105-000 | $250,000.00 | IDIQ Civil Engineering Land Utility Surveying | VIEW + |
| MWM DesignGroup Inc | 22-105-000 | $250,000.00 | Amendment 1 | VIEW + |
| Gessner Engineering LLC | 22-104-000 | $250,000.00 | Amendment 1 | VIEW + |
| Gessner Engineering LLC | 22-104-000 | $250,000.00 | IDIQ Civil Engineering and Land Utility Survey | VIEW + |
| Vickrey & Associates LLC | 22-103-000 | $250,000.00 | IDIQ Civil Engineering and Land Utility Survey | VIEW + |
| Vickrey & Associates LLC | 22-103-000 | $250,000.00 | Amendment 1 | VIEW + |
| Vickrey & Associates LLC | 22-103-000 | $6,500.00 | Assignment 1 | VIEW + |
| Jose I Guerra Inc | 22-102-000 | $250,000.00 | Amendment 1 | VIEW + |
| Jose I Guerra Inc | 22-102-000 | $250,000.00 | IDIQ Civil Engineering and Land Utility Survey | VIEW + |
| Freese and Nichols Inc | 22-101-000 | $250,000.00 | IDIQ Civil Engineering and Land Utility Survey | VIEW + |
| Freese and Nichols, Inc | 22-101-000 | $22,955.00 | Assignment 1 | VIEW + |
| Freese and Nichols Inc | 22-101-000 | $250,000.00 | Amendment 1 | VIEW + |
| Freese and Nichols Inc | 22-101-000 | $106,492.00 | Assignment 3 | VIEW + |
| Freese and Nichols Inc | 22-101-000 | $119,885.45 | Assignment 2 | VIEW + |
| Walter P. Moore Inc | 22-100-000 | $18,750.00 | Assignment 3 | VIEW + |
| Walter P. Moore Inc | 22-100-000 | $16,500.00 | Assignment 4 | VIEW + |
| Walter P Moore Inc | 22-100-000 | $0.00 | Amendment 1 to Assignment 3 | VIEW + |
| Walter P Moore Inc | 22-100-000 | $11,500.00 | Assignment 6 | VIEW + |
| Walter P Moore Inc | 22-100-000 | $53,701.10 | Assignment 5 | VIEW + |
| Walter P Moore Inc | 22-100-000 | $9,500.00 | Assignment 2 | VIEW + |
| Walter P Moore Inc | 22-100-000 | $38,250.00 | Assignment 1 | VIEW + |
| Walter P Moore Inc | 22-100-000 | $250,000.00 | Amendment 1 | VIEW + |
| Walter P Moore and Associates Inc | 22-100-000 | $250,000.00 | IDIQ Civil Engineering and Land Utility Survey | VIEW + |
| Cobb Fendley & Associates Inc | 22-099-000 | $99,320.00 | Assignment 1 | VIEW + |
| Cobb Fendley & Associates Inc | 22-099-000 | $250,000.00 | IDIQ Civil Engineering Land Utility Surveying | VIEW + |
| Cobb Fendley & Associates Inc | 22-099-000 | $0.00 | Amendment 1 to Assignment 3 | VIEW + |
| Cobb Fendley & Associates Inc | 22-099-000 | $67,012.00 | Assignment 4 | VIEW + |
| Cobb Fendley & Associates Inc | 22-099-000 | $37,156.00 | Assignment 2 | VIEW + |
| Cobb Fendley & Associates Inc | 22-099-000 | $46,512.00 | Assignment 3 | VIEW + |
| Cobb Fendley & Associates Inc | 22-099-000 | $27,400.00 | Assignment 6 | VIEW + |
| Cobb Fendley & Associates Inc | 22-099-000 | $0.00 | Amendment 3 to Assignment 3 | VIEW + |
| Cobb Fendley & Associates Inc | 22-099-000 | $175,173.50 | Assignment 5 | VIEW + |
| Cobb Fendley & Associates Inc | 22-099-000 | $250,000.00 | Amendment 1 | VIEW + |
| Cobb Fendley & Associates Inc | 22-099-000 | $0.00 | Amendment 2 to Assignment 3 | VIEW + |
| Cobb Fendley and Associates Inc | 22-099-000 | $32,737.50 | Assignment 7 | VIEW + |
| Arias & Associates Inc | 22-098-000 | $15,812.50 | Assignment 3 | VIEW + |
| Arias & Associates Inc | 22-098-000 | $250,000.00 | Amendment 1 | VIEW + |
| Arias & Associates Inc | 22-098-000 | $0.00 | Amendment 1 to Assignment 2 | VIEW + |
| Arias & Associates Inc | 22-098-000 | $12,240.00 | Assignment 2 | VIEW + |
| Arias & Associates Inc | 22-098-000 | $250,000.00 | IDIQ Geotechnical & Construction Materials Testing | VIEW + |
| Arias & Associates Inc | 22-098-000 | $4,817.50 | Assignment 1 | VIEW + |
| Gessner Engineering LLC | 22-097-000 | $250,000.00 | IDIQ Geotechnical & Construction Materials Testing | VIEW + |
| Gessner Engineering LLC | 22-097-000 | $250,000.00 | Amendment 1 | VIEW + |
| ECS Southwest LLP | 22-096-000 | $250,000.00 | Amendment 1 | VIEW + |
| ECS Southwest LLP | 22-096-000 | $9,600.00 | Amendment 1 to Assignment 1 | VIEW + |
| ECS Southwest, LLP | 22-096-000 | $5,750.00 | Amendment 2 to Assignment 1 | VIEW + |
| ECS Southwest LLP | 22-096-000 | $96,850.00 | Assignment 1 | VIEW + |
| ECS Southwest LLP | 22-096-000 | $250,000.00 | IDIQ Geotechnical & Construction Materials Testing | VIEW + |
| J T Vaughn Construction LLC | 22-095-000 | $5,455,000.00 | Construction Manager at Risk | VIEW + |
| J T Vaughn Construction LLC | 22-095-000 | $0.00 | Amendment 1 | VIEW + |
| J. T. Vaughn Construction, LLC | 22-095-000 | $0.00 | Amendment 3 | VIEW + |
| J T Vaughn Construction LLC | 22-095-000 | $497,727.00 | Amendment 2 | VIEW + |
| MLA Labs, Inc. | 22-094-000 | $250,000.00 | Amendment 1 | VIEW + |
| MLA Labs, Inc. | 22-094-000 | $250,000.00 | IDIQ Geotechnical & Construction Materials Testing | VIEW + |
| Fugro USA Land Inc a wholly owned subsidiary of Fugro N V | 22-093-000 | $250,000.00 | IDIQ Geotechnical & Construction Materials Testing | VIEW + |
| Braun Intertec Corporation | 22-092-000 | $250,000.00 | IDIQ Geotechnical & Construction Materials Testing | VIEW + |
| Braun Intertec Corporation | 22-092-000 | $250,000.00 | Amendment 1 | VIEW + |
| Raba Kistner Inc | 22-091-000 | $9,669.35 | Assignment 5 | VIEW + |
| Raba Kistner Inc | 22-091-000 | $250,000.00 | Amendment 1 | VIEW + |
| Raba Kistner Inc | 22-091-000 | $0.00 | Amendment 2 to Assignment 1 | VIEW + |
| Raba Kistner Inc | 22-091-000 | $44,654.00 | Assignment 8 | VIEW + |
| Raba Kistner Inc | 22-091-000 | $42,754.80 | Assignment 6 | VIEW + |
| Raba Kistner Inc | 22-091-000 | $6,604.00 | Assignment 7 | VIEW + |
| Raba Kistner Inc | 22-091-000 | $250,000.00 | IDIQ Geotechnical & Construction Materials Testing | VIEW + |
| Raba Kistner Inc | 22-091-000 | $1,428.90 | Assignment 4 | VIEW + |
| Raba Kistner Inc | 22-091-000 | $27,468.65 | Assignment 2 | VIEW + |
| Raba Kistner Inc | 22-091-000 | $15,900.00 | Assignment 1 | VIEW + |
| Raba Kistner Inc | 22-091-000 | $12,900.00 | Amendment 1 to Assignment 1 | VIEW + |
| Raba Kistner Inc | 22-091-000 | $61,069.25 | Assignment 3 | VIEW + |
| Professional Service Industries Inc | 22-090-000 | $2,445.00 | Assignment 1 | VIEW + |
| Professional Service Industries Inc | 22-090-000 | $250,000.00 | IDIQ Geotechnical & Construction Materials Testing | VIEW + |
| Professional Service Industries Inc | 22-090-000 | $26,500.00 | Assignment 2 | VIEW + |
| Professional Service Industries Inc | 22-090-000 | $250,000.00 | Amendment 1 | VIEW + |
| Kleinfedler Inc | 22-089-000 | $250,000.00 | Amendment 1 | VIEW + |
| Kleinfelder Inc | 22-089-000 | $203,475.32 | Amendment 2 | VIEW + |
| Kleinfelder Inc | 22-089-000 | $51,400.00 | Assignment 3 | VIEW + |
| Kleinfelder Inc | 22-089-000 | $53,488.00 | Amendment 1 to Assignment 2 | VIEW + |
| Kleinfelder Inc | 22-089-000 | $54,968.00 | Assignment 2 | VIEW + |
| Kleinfelder Inc | 22-089-000 | $203,475.32 | Assignment 4 | VIEW + |
| Kleinfelder Inc | 22-089-000 | $47,500.00 | Assignment 5 | VIEW + |
| Kleinfelder Inc | 22-089-000 | $16,902.50 | Assignment 1 | VIEW + |
| Kleinfedler Inc | 22-089-000 | $250,000.00 | IDIQ Geotechnical and Construction Materials Testing | VIEW + |
| Johnson Controls Inc | 22-085-000 | $3,835,373.00 | Energy Performance Contract | VIEW + |
| Johnson Controls Inc | 22-085-000 | $81,871.00 | Amendment 1 | VIEW + |
| Johnson Controls Inc | 22-085-000 | $19,379.00 | Amendment 2 | VIEW + |
| E3 Entegral Solutions Inc | 22-084-000 | $3,893,371.00 | Energy Efficiency Agreement | VIEW + |
| Stanley Consultants Inc | 22-082-000 | $1,236,000.00 | Professional Services (Commissioning) | VIEW + |
| Stanley Consultants Inc | 22-082-000 | $0.00 | Amendment 1 | VIEW + |
| Stanley Consultants, Inc. | 22-082-000 | $0.00 | Amendment 3 | VIEW + |
| Stanley Consultants Inc | 22-082-000 | $390,500.00 | Amendment 2 | VIEW + |
| Western States Fire Protection | 22-081-000 | $689,278.00 | Service Contract | VIEW + |
| Energy Testing and Balance Inc | 22-080-000 | $250,000.00 | IDIQ HVAC Testing and Balance | VIEW + |
| Energy Testing and Balance Inc | 22-080-000 | $9,150.00 | Assignment 1 | VIEW + |
| Energy Testing and Balance Inc | 22-080-000 | $168,500.00 | Assignment 2 | VIEW + |
| Energy Testing and Balance Inc | 22-080-000 | $250,000.00 | Amendment 1 | VIEW + |
| Atlas Technical Consultants LLC | 22-077-000 | $250,000.00 | Amendment 1 | VIEW + |
| Energy Engineering Associates Inc | 22-077-000 | $92,493.00 | Assignment 5 | VIEW + |
| Atlas Technical Consultants LLC | 22-077-000 | $250,000.00 | IDIQ Geotechnical and Construction Materials Testing | VIEW + |
| Stantec Consulting Services Inc | 22-076-000 | $250,000.00 | IDIQ Civil Engineering and Land Utility Survey | VIEW + |
| Surveying and Mapping LLC (SAM) | 22-075-000 | $16,330.00 | Assignment 2 | VIEW + |
| Surveying & Mapping LLC | 22-075-000 | $55,194.75 | Assignment 1 | VIEW + |
| Surveying and Mapping LLC (SAM) | 22-075-000 | $27,000.00 | Assignment 4 | VIEW + |
| Surveying and Mapping LLC (SAM) | 22-075-000 | $35,200.00 | Assignment 3 | VIEW + |
| Surveying & Mapping, LLC (SAM) | 22-075-000 | $230,366.60 | Assignment 5 | VIEW + |
| Surveying and Mapping LLC (SAM) | 22-075-000 | $250,000.00 | Amendment 1 | VIEW + |
| Stantec Consulting Services Inc | 22-075-000 | $250,000.00 | Amendment 1 | VIEW + |
| TAB Technologies LLC | 22-074-000 | $5,166.00 | Assignment 9 | VIEW + |
| TAB Technologies LLC | 22-074-000 | $40,567.00 | Assignment 10 | VIEW + |
| TAB Technologies LLC | 22-074-000 | $5,464.00 | Assignment 8 | VIEW + |
| TAB Technologies LLC | 22-074-000 | $69,574.00 | Assignment 6 | VIEW + |
| TAB Technologies LLC | 22-074-000 | $99,845.00 | Assignment 7 | VIEW + |
| TAB Technologies LLC | 22-074-000 | $0.00 | Amendment 1 to Assignment 5 | VIEW + |
| TAB Technologies LLC | 22-074-000 | $29,384.00 | Assignment 11 | VIEW + |
| TAB Technologies LLC | 22-074-000 | $0.00 | Amendment 1 to Assignment 6 | VIEW + |
| TAB Technologies LLC | 22-074-000 | $250,000.00 | Amendment 1 | VIEW + |
| TAB Technologies LLC | 22-074-000 | $93,786.00 | Assignment 5 | VIEW + |
| TAB Technologies LLC | 22-074-000 | $0.00 | Amendment 1 to Assignment 4 | VIEW + |
| TAB Technologies LLC | 22-074-000 | $5,024.00 | Assignment 4 | VIEW + |
| TAB Technologies LLC | 22-074-000 | $99,029.00 | Assignment 1 | VIEW + |
| Surveying and Mapping LLC (SAM) | 22-074-000 | $250,000.00 | IDIQ Civil Engineering Land Utility Surveying | VIEW + |
| TAB Technologies LLC | 22-074-000 | $250,000.00 | IDIQ HVAC Testing & Balancing | VIEW + |
| TAB Technologies LLC | 22-074-000 | $35,642.00 | Assignment 3 | VIEW + |
| TAB Technologies LLC | 22-074-000 | $16,519.00 | Assignment 2 | VIEW + |
| Terracon Consultants Inc | 22-073-000 | $15,461.00 | Assignment 2 | VIEW + |
| Terracon Consultants Inc | 22-073-000 | $250,000.00 | IDIQ Geotechnical & Construction Materials Testing | VIEW + |
| Terracon Consultants Inc | 22-073-000 | $11,178.00 | Assignment 1 | VIEW + |
| Terracon Consultants Inc | 22-073-000 | $2,130.00 | Amendment No. 1 to Assignment No. 1 | VIEW + |
| Terracon Consultants Inc | 22-073-000 | $5,350.00 | Assignment 3 | VIEW + |
| Terracon Consultants Inc | 22-073-000 | $7,373.75 | Assignment 4 | VIEW + |
| Terracon Consultants Inc | 22-073-000 | $33,925.00 | Assignment 5 | VIEW + |
| Terracon Consultants Inc | 22-073-000 | $84,408.00 | Assignment 8 | VIEW + |
| Terracon Consultants Inc | 22-073-000 | $42,000.00 | Assignment 7 | VIEW + |
| Terracon Consultants, Inc | 22-073-000 | $0.00 | Amendment 1 to Assignment 2 | VIEW + |
| Terracon Consultants Inc | 22-073-000 | $9,000.00 | Assignment 6 | VIEW + |
| Terracon Consultants, Inc | 22-073-000 | $13,795.00 | Assignment 9 | VIEW + |
| Terracon Consultants Inc | 22-073-000 | $0.00 | Amendment 1 to Assignment 5 | VIEW + |
| Terracon Consultants Inc | 22-073-000 | $0.00 | Amendment 1 to Assignment 7 | VIEW + |
| Terracon Consultants, Inc | 22-073-000 | $250,000.00 | Amendment 1 | VIEW + |
| Terracon Consultants Inc | 22-073-000 | $230,000.00 | Assignment 10 | VIEW + |
| TD Industries Inc | 22-069-000 | $500,000.00 | Amendment 1 | VIEW + |
| TD Industries Inc | 22-069-000 | $500,000.00 | Amendment 1 | VIEW + |
| TDIndustries Inc | 22-069-000 | $500,000.00 | Service Contract | VIEW + |
| The Brandt Companies LLC | 22-068-000 | $500,000.00 | Service Contract | VIEW + |
| The Brandt Companies LLC | 22-068-000 | $500,000.00 | Amendment 1 | VIEW + |
| The Brandt Companies LLC | 22-068-000 | $500,000.00 | Amendment 2 | VIEW + |
| The Brandt Companies LLC | 22-068-000 | $200,000.00 | Amendment 3 | VIEW + |
| Beard Integrated Systems Inc | 22-067-000 | $300,000.00 | Amendment 3 | VIEW + |
| Beard Integrated Systems Inc | 22-067-000 | $500,000.00 | Amendment 2 | VIEW + |
| Beard Integrated Systems Inc | 22-067-000 | $1,000,000.00 | Amendment 1 | VIEW + |
| Beard Integrated Systems Inc. | 22-067-000 | $1,000,000.00 | Service Contract | VIEW + |
| Raba Kistner Inc | 22-066-000 | $250,000.00 | IDIQ Environmental Services | VIEW + |
| Raba Kistner Inc | 22-066-000 | $8,696.00 | Assignment 2 | VIEW + |
| Raba Kistner Inc | 22-066-000 | $3,875.00 | Assignment 1 | VIEW + |
| Raba Kistner Inc | 22-066-000 | $38,500.00 | Assignment 3 | VIEW + |
| Raba Kistner Inc | 22-066-000 | $250,000.00 | Amendment 1 | VIEW + |
| Raba Kistner Inc | 22-066-000 | $11,650.00 | Assignment 6 | VIEW + |
| Raba Kistner Inc | 22-066-000 | $8,145.00 | Assignment 4 | VIEW + |
| Raba Kistner Inc | 22-066-000 | $9,200.00 | Assignment 5 | VIEW + |
| Terracon Consultants, Inc | 22-065-000 | $17,560.00 | Assignment 8 | VIEW + |
| Terracon Consultants, Inc | 22-065-000 | $0.00 | Amendment 2 to Assignment 6 | VIEW + |
| Terracon Consultants Inc | 22-065-000 | $0.00 | Amendment 1 to Assignment 7 | VIEW + |
| Terracon Consultants Inc | 22-065-000 | $17,514.00 | Assignment 10 | VIEW + |
| Terracon Consultants Inc | 22-065-000 | $2,750.00 | Assignment 9 | VIEW + |
| Terracon Consultants Inc | 22-065-000 | $250,000.00 | Amendment 1 | VIEW + |
| Terracon Consultants Inc | 22-065-000 | $0.00 | Amendment 1 to Assignment 6 | VIEW + |
| Terracon Consultants, Inc | 22-065-000 | $22,000.00 | Assignment 7 | VIEW + |
| Terracon Consultants, Inc | 22-065-000 | $0.00 | Amendment 1 to Assignment 2 | VIEW + |
| Terracon Consultants Inc | 22-065-000 | $75,870.00 | Assignment 6 | VIEW + |
| Terracon Consultants Inc | 22-065-000 | $49,197.40 | Assignment 5 | VIEW + |
| Terracon Consultants Inc | 22-065-000 | $8,460.00 | Assignment 4 | VIEW + |
| Terracon Consultants Inc | 22-065-000 | $9,345.00 | Assignment 3 | VIEW + |
| Terracon Consultants Inc | 22-065-000 | $5,275.00 | Assignment 2 | VIEW + |
| Terracon Consultants Inc | 22-065-000 | $250,000.00 | IDIQ Environmental Engineering | VIEW + |
| Terracon Consultants Inc | 22-065-000 | $2,960.00 | Assignment 1 | VIEW + |
| Weston Solutions Inc | 22-064-000 | $250,000.00 | IDIQ Environmental Engineering Services | VIEW + |
| Weston Solutions Inc | 22-064-000 | $250,000.00 | Amendment 1 | VIEW + |
| Kleinfedler Inc | 22-063-000 | $250,000.00 | Amendment 1 | VIEW + |
| Kleinfelder Inc | 22-063-000 | $3,450.00 | Assignment 1 | VIEW + |
| Kleinfelder Inc | 22-063-000 | $57,900.00 | Assignment 2 | VIEW + |
| Kleinfelder Inc | 22-063-000 | $128,638.00 | Amendment 1 to Assignment 2 | VIEW + |
| Kleinfelder Inc | 22-063-000 | ($32,628.00) | Amendment 2 to Assignment 2 | VIEW + |
| Kleinfelder Inc | 22-063-000 | $2,500.00 | Amendment 3 to Assignment 2 | VIEW + |
| Kleinfelder Inc | 22-063-000 | $46,257.00 | Assignment 3 | VIEW + |
| Kleinfelder Inc | 22-063-000 | $250,000.00 | IDIQ for Environmental Engineering Services | VIEW + |
| Stanley Consultants Inc | 22-062-000 | $250,000.00 | IDIQ Environmental Engineering Services | VIEW + |
| Stanley Consultants Inc | 22-062-000 | $15,000.00 | Assignment 1 | VIEW + |
| Stanley Consultants Inc | 22-062-000 | $250,000.00 | Amendment 1 Renewal | VIEW + |
| Stanley Consultants inc | 22-062-000 | $0.00 | Amendment 1 to Assignment 1 | VIEW + |
| Stanley Consultants Inc. | 22-062-000 | $43,565.00 | Amendment No. 1 to Assignment No. 2 | VIEW + |
| Stanley Consultants Inc | 22-062-000 | $43,565.00 | Amendment No. 1 to Assignment No. 2 | VIEW + |
| Stanley Consultants Inc | 22-062-000 | $75,300.00 | Assignment 2 | VIEW + |
| ERC Environmental & Construction Services Inc dba ERC | 22-061-000 | $0.00 | Amendment 1 to Assignment 1 | VIEW + |
| ERC Environmental and Construction Services Inc dba ERC | 22-061-000 | $28,400.00 | Assignment 4 | VIEW + |
| ERC Environmental and Construction Services Inc dba ERC | 22-061-000 | $13,365.00 | Amendment 1 to Assignment 4 | VIEW + |
| ERC Environmental & Construction | 22-061-000 | $250,000.00 | Amendment 1 RENEWAL | VIEW + |
| ERC Environmental & Construction Services Inc dba ERC | 22-061-000 | $2,850.00 | Amendment 1 to Assignment 2 | VIEW + |
| ERC Environmental & Construction Services Inc dba ERC | 22-061-000 | $18,494.00 | Assignment 2 | VIEW + |
| ERC Environmental & Construction Services, Inc. dba ERC | 22-061-000 | $21,366.00 | Assignment 3 | VIEW + |
| ERC Environmental & Construction Services Inc dba ERC | 22-061-000 | $250,000.00 | IDIQ for Environmental Engineering Services | VIEW + |
| ERC Environmental & Construction Services Inc dba ERC | 22-061-000 | $4,560.00 | Assignment 1 | VIEW + |
| Wood Environment & Infrastructure Solutions Inc | 22-060-000 | $123,364.00 | Assignment 4 | VIEW + |
| Wood Environment and Infrastructure Solutions Inc | 22-060-000 | $13,618.00 | Assignment 3 | VIEW + |
| Wood Environment and Infrastructure Solutions Inc | 22-060-000 | $18,308.00 | Assignment 2 | VIEW + |
| Wood Environment and Infrastructure Solutions Inc | 22-060-000 | $250,000.00 | IDIQ Environmental Engineering Services | VIEW + |
| Wood Environment & Infrastructure Solutions Inc | 22-060-000 | $47,966.00 | Assignment 1 | VIEW + |
| WSP USA Environment & Infrastructure Inc | 22-060-000 | $0.00 | Amendment 1 | VIEW + |
| Wood Environment & Infrastructure Solutions Inc | 22-060-000 | $9,370.00 | Assignment 5 | VIEW + |
| Wood Environment & Infrastructure Solutions Inc | 22-060-000 | $37,310.00 | Assignment 6 | VIEW + |
| WSP USA Environment & Infrastructure Inc. | 22-060-000 | $10,590.00 | Amendment 1 to Assignment 5 | VIEW + |
| WSP USA Environment & Infrastructure Solutions Inc | 22-060-000 | $5,724.00 | Assignment 8 | VIEW + |
| WSP USA Environment & Infrastructure Solutions Inc | 22-060-000 | $5,526.85 | Assignment 9 | VIEW + |
| WSP USA Environment & Infrastructure Solutions Inc | 22-060-000 | $5,526.85 | Assignment 9 | VIEW + |
| WSP USA Environment & Infrastructure Inc | 22-060-000 | $250,000.00 | Amendment 1 | VIEW + |
| WSP USA Environment & Infrastructure Inc | 22-060-000 | $250,000.00 | Amendment 2 | VIEW + |
| TTL Inc | 22-059-000 | $250,000.00 | Amendment 1 | VIEW + |
| TTL Inc | 22-059-000 | $250,000.00 | IDIQ Environmental Engineering Services | VIEW + |
| Baer Engineering and Environmental Consulting Inc | 22-058-000 | $250,000.00 | IDIQ for Environmental Engineering Services | VIEW + |
| Baer Engineering and Environmental Consulting Inc | 22-058-000 | $4,907.96 | Assignment 1 | VIEW + |
| Baer Engineering and Environmental Consulting Inc | 22-058-000 | $9,719.85 | Assignment 2 | VIEW + |
| Baer Engineering and Environmental Consulting Inc | 22-058-000 | $250,000.00 | Amendment 1 | VIEW + |
| Environmental Science and Engineering Partners LLC | 22-057-000 | $250,000.00 | Amendment 1 Renewal | VIEW + |
| Environmental Science and Engineering Partners LLC | 22-057-000 | $250,000.00 | Amendment 1 Renewal | VIEW + |
| Environmental Science and Engineering Partners LLC | 22-057-000 | $250,000.00 | IDIQ Environmental | VIEW + |
| Garver LLC | 22-055-000 | $400,000.00 | IDIQ Architectural Services | VIEW + |
| Garver LLC | 22-055-000 | $400,000.00 | Amendment 1 | VIEW + |
| Negrete & Kolar Architects LLP | 22-054-000 | $400,000.00 | IDIQ Architectural | VIEW + |
| Negrete & Kolar Architects LLP | 22-054-000 | $400,000.00 | Amendment 1 | VIEW + |
| Method Architecture LLC | 22-053-000 | $400,000.00 | IDIQ Architectural Services | VIEW + |
| Method Architecture LLC | 22-053-000 | $400,000.00 | Amendment 1 | VIEW + |
| Wiss Janney Elstner Associates Inc | 22-052-000 | $49,500.00 | Assignment 2 | VIEW + |
| Wiss Janney Elstner Associates Inc. | 22-052-000 | $400,000.00 | IDIQ Architectural Services | VIEW + |
| Wiss Janney Elstner Associates Inc | 22-052-000 | $7,500.00 | Assignment 1 | VIEW + |
| Wiss Janney Elstner Associates Inc | 22-052-000 | $400,000.00 | Amendment 1 | VIEW + |
| MWM DesignGroup Inc | 22-051-000 | $400,000.00 | IDIQ Architectural Services | VIEW + |
| MWM DesignGroup Inc | 22-051-000 | $400,000.00 | Amendment 1 | VIEW + |
| The Lawrence Group Architects of Austin Inc | 22-050-000 | $400,000.00 | Amendment 1 | VIEW + |
| The Lawrence Group Architects of Austin Inc | 22-050-000 | $102,240.00 | Assignment 1 | VIEW + |
| The Lawrence Group Architects of Austin Inc | 22-050-000 | $50,000.00 | Assignment 3 | VIEW + |
| The Lawrence Group Architects of Austin Inc | 22-050-000 | $85,000.00 | Assignment 2 | VIEW + |
| The Lawrence Group Architects of Austin Inc | 22-050-000 | $4,125.00 | Amendment No. 1 to Assignment No. 1 | VIEW + |
| The Lawrence Group Architects of Austin Inc | 22-050-000 | $0.00 | Amendment No. 2 to Assignment No. 1 | VIEW + |
| The Lawrence Group Architects of Austin Inc | 22-050-000 | $0.00 | Amendment 3 to Assignment 1 | VIEW + |
| The Lawrence Group Architects of Austin Inc | 22-050-000 | $45,000.00 | Amendment 1 to Assignment 3 | VIEW + |
| The Lawrence Group Architects of Austin Inc | 22-050-000 | $0.00 | Amendment 1 to Assignment 2 | VIEW + |
| The Lawrence Group Architects of Austin Inc | 22-050-000 | $400,000.00 | IDIQ Architectural | VIEW + |
| Kirksey Architects Inc | 22-049-000 | $400,000.00 | IDIQ Architectural Services | VIEW + |
| Kirksey Architects Inc | 22-049-000 | $400,000.00 | Amendment 1 | VIEW + |
| Kirksey Architects Inc | 22-049-000 | $4,500.00 | Amendment 1 to Assignment 1 | VIEW + |
| Kirksey Architects Inc | 22-049-000 | $70,000.00 | Assignment 1 | VIEW + |
| Kirksey Architects Inc | 22-049-000 | $0.00 | Amendment 1 to Assignment 2 | VIEW + |
| Kirksey Architects Inc | 22-049-000 | $152,500.00 | Assignment 2 | VIEW + |
| McKinney Architects Inc dba McKinney York Architects | 22-048-000 | $137,500.00 | Assignment 4 | VIEW + |
| McKinney York Architects Inc dba McKinney York Architects | 22-048-000 | $65,000.00 | Assignment 3 | VIEW + |
| McKinney Architects Inc dba McKinney York Architects | 22-048-000 | $46,320.00 | Assignment 5 | VIEW + |
| McKinney Architects Inc dba McKinney York Architects | 22-048-000 | $20,000.00 | Amendment 1 to Assignment 3 | VIEW + |
| McKinney Architects Inc dba McKinney York Architects | 22-048-000 | $108,000.00 | Assignment 6 | VIEW + |
| McKinney Architects Inc dba McKinney York Architects | 22-048-000 | $300,000.00 | Assignment 2 | VIEW + |
| McKinney Architects Inc dba McKinney York Architects | 22-048-000 | $400,000.00 | Amendment 1 | VIEW + |
| McKinney Architects Inc dba McKinney York Architects | 22-048-000 | $400,000.00 | IDIQ Architectural Services | VIEW + |
| McKinney York Architects Inc dba McKinney York Architects | 22-048-000 | $10,000.00 | Assignment 1 | VIEW + |
| Pfluger Architects Inc | 22-047-000 | $400,000.00 | IDIQ Architectural Services | VIEW + |
| Pfluger Architects Inc | 22-047-000 | $400,000.00 | Amendment 1 | VIEW + |
| AECOM Technical Services Inc | 22-046-000 | $4,440.00 | Amendment 2 to Assignment 1 | VIEW + |
| AECOM Technical Services Inc | 22-046-000 | $24,443.00 | Amendment 1 to Assignment 1 | VIEW + |
| AECOM Technical Services Inc | 22-046-000 | $358,320.00 | Assignment 1 | VIEW + |
| AECOM Technical Services Inc | 22-046-000 | $400,000.00 | IDIQ Architectural Services | VIEW + |
| AECOM Technical Services Inc | 22-046-000 | $400,000.00 | Amendment 1 | VIEW + |
| Powers Brown Architecture NA LLC | 22-045-000 | $400,000.00 | Amendment 1 | VIEW + |
| Powers Brown Architecture NA LLC | 22-045-000 | $400,000.00 | IDIQ Architectural Services | VIEW + |
| Powers Brown Architecture NA LLC | 22-045-000 | $94,910.00 | Assignment 1 | VIEW + |
| Madeline Anz Slay Architecture LLC dba SLAY Architecture | 22-044-000 | $400,000.00 | IDIQ Architectural Services | VIEW + |
| Madeline Anz Slay Architecture LLC dba SLAY Architecture | 22-044-000 | $400,000.00 | Amendment 1 | VIEW + |
| Jacobs Engineering Group Inc. | 22-043-000 | $400,000.00 | Amendment 1 | VIEW + |
| Jacobs Engineering Group Inc | 22-043-000 | $400,000.00 | IDIQ Architectural Services | VIEW + |
| Jacobs Engineering Group Inc | 22-043-000 | $17,736.00 | Amendment 1 to Assignment 2 | VIEW + |
| Jacobs Engineering Group Inc | 22-043-000 | $11,000.00 | Amendment 2 to Assignment 2 | VIEW + |
| Jacobs Engineering Group Inc | 22-043-000 | $41,206.00 | Assignment 1 | VIEW + |
| Jacobs Engineering Group Inc | 22-043-000 | $99,651.00 | Assignment 2 | VIEW + |
| Walker Parking Consultants/Engineers, Inc., dba Walker Consultants | 22-042-000 | $12,000.00 | Assignment 4 | VIEW + |
| Walker Parking Consultants Engineers Inc dba Walker Consultants | 22-042-000 | $400,000.00 | IDIQ Architectural Services | VIEW + |
| Walker Consultants/Engineers Inc dba Walker Consultants | 22-042-000 | $10,600.00 | Assignment 2 | VIEW + |
| Walker Parking Consultants Engineers Inc dba Walker Consultants | 22-042-000 | $13,750.00 | Assignment 1 | VIEW + |
| Walker Parking Consultants/Engineers, Inc., dba Walker Consultant | 22-042-000 | $400,000.00 | Amendment 1 | VIEW + |
| Walker Parking Consultants Engineers Inc dba Walker Consultants | 22-042-000 | $52,500.00 | Assignment 3 | VIEW + |
| Graeber Simmons & Cowan Inc a wholly owned subsidiary of Method Architecture LLC | 22-041-000 | $0.00 | Amendment 1 | VIEW + |
| Graeber Simmons & Cowan Inc | 22-041-000 | $400,000.00 | IDIQ Architectural Services | VIEW + |
| Graeber Simmons & Cowan Inc a wholly owned subsidiary of Method Architecture LLC | 22-041-000 | $400,000.00 | Amendment 2 | VIEW + |
| Sunland Group Inc | 22-040-000 | $37,780.05 | Assignment 2 | VIEW + |
| Sunland Group Inc | 22-040-000 | $8,526.32 | Assignment 3 | VIEW + |
| Sunland Group Inc | 22-040-000 | $327,776.91 | Amendment No. 4 | VIEW + |
| Sunland Group Inc | 22-040-000 | $0.00 | Amendment 1 to Assignment 3 | VIEW + |
| Sunland Group Inc | 22-040-000 | $400,000.00 | IDIQ Architectural Services | VIEW + |
| Sunland Group Inc | 22-040-000 | $46,600.81 | Assignment 1 | VIEW + |
| Sunland Group Inc | 22-040-000 | $400,000.00 | Amendment 1 | VIEW + |
| Casabella Architects Inc | 22-039-000 | $400,000.00 | Amendment 1 | VIEW + |
| Casabella Architects Inc | 22-039-000 | $400,000.00 | Amendment 1 | VIEW + |
| Casabella Architects Inc | 22-039-000 | $400,000.00 | IDIQ for Architectural Services | VIEW + |
| CasaBella Architects Inc | 22-039-000 | $186,744.00 | Assignment 3 | VIEW + |
| CasaBella Architects Inc | 22-039-000 | $82,482.00 | Assignment 2 | VIEW + |
| CasaBella Architects Inc | 22-039-000 | $98,000.00 | Assignment 1 | VIEW + |
| M Arthur Gensler | 22-038-000 | $0.00 | Amendment 1 to Assignment 1 | VIEW + |
| M Arthur Gensler Jr & Associates | 22-038-000 | $400,000.00 | IDIQ Architectural | VIEW + |
| M Arthur Gensler Jr & Associates Inc | 22-038-000 | $400,000.00 | Amendment 1 | VIEW + |
| M Arthur Gensler Jr & Associates | 22-038-000 | $146,220.00 | Assignment 1 | VIEW + |
| Freese and Nichols Inc | 22-037-000 | $97,797.00 | Assignment 2 | VIEW + |
| Freese and Nichols Inc | 22-037-000 | $400,000.00 | Amendment 1 | VIEW + |
| Freese and Nichols Inc | 22-037-000 | $156,250.00 | Assignment 1 | VIEW + |
| Freese and Nichols Inc | 22-037-000 | $400,000.00 | IDIQ Architectural Services | VIEW + |
| Freese and Nichols Inc | 22-037-000 | $78,945.00 | Assignment 3 | VIEW + |
| Freese & Nichols Inc | 22-037-000 | $0.00 | Amendment 1 to Assignment 1 | VIEW + |
| Freese and Nichols Inc | 22-037-000 | $0.00 | Amendment 2 to Assignment 1 | VIEW + |
| Carter Design Associates Inc dba Carter Design Associates | 22-036-000 | $28,224.00 | Assignment 7 | VIEW + |
| Carter Design Associates Inc dba Carter Design Associates | 22-036-000 | $0.00 | Amendment No. 4 to Assignment No. 1 | VIEW + |
| Carter Design Associates | 22-036-000 | $22,240.00 | Amendment 2 to Assignment No 6 | VIEW + |
| Carter Design Associates Inc dba Carter Design Associates | 22-036-000 | $6,400.00 | Amendment 3 to Assignment 1 | VIEW + |
| Carter Design Associates Inc dba Carter Design Associates | 22-036-000 | $0.00 | Amendment 1 to Assignment 3 | VIEW + |
| Carter Design Associates Inc dba Carter Design Associates | 22-036-000 | $18,000.00 | Amendment 1 to Assignment 1 | VIEW + |
| Carter Design Associates Inc dba Carter Design Associates | 22-036-000 | $26,680.00 | Amendment 1 to Assignment 6 | VIEW + |
| Carter Design Associates Inc dba Carter Design Associates | 22-036-000 | $30,335.00 | Amendment 2 to Assignment 1 | VIEW + |
| Carter Design Associates Inc dba Carter Design Associates | 22-036-000 | $15,120.00 | Assignment 6 | VIEW + |
| Carter Design Associates Inc dba Carter Design Associates | 22-036-000 | $73,000.00 | Assignment 5 | VIEW + |
| Carter Design Associates Inc dba Carter Design Associates | 22-036-000 | $400,000.00 | IDIQ Architectural Services | VIEW + |
| Carter Design Associates Inc dba Carter Design Associates | 22-036-000 | $7,059.00 | Assignment 2 | VIEW + |
| Carter Design Associates | 22-036-000 | $29,139.00 | Assignment 1 | VIEW + |
| Carter Design Associates Inc dba Carter Design Associates | 22-036-000 | $400,000.00 | Amendment 1 | VIEW + |
| Carter Design Associates Inc dba Carter Design Associates | 22-036-000 | $196,000.00 | Assignment 4 | VIEW + |
| Carter Design Associates Inc dba Carter Design Associates | 22-036-000 | $19,800.00 | Assignment 3 | VIEW + |
| Michael Baker International and Huitt Zollars JV | 22-035-000 | $3,353,432.25 | Amendment 2 | VIEW + |
| Michael Baker International and Huitt Zollars Joint Venture | 22-035-000 | $161,280.00 | Amendment 3 | VIEW + |
| Michael Baker International Huitt Zollars Joint Venture | 22-035-000 | $5,972,697.64 | Amendment 4 | VIEW + |
| Michael Baker International Huitt Zollars Joint Venture | 22-035-000 | $168,000.00 | Amendment 5 | VIEW + |
| Michael Baker International and Huittz-Zollars Inc | 22-035-000 | $2,596,038.00 | Amendment 6 | VIEW + |
| Michael Baker International and Huitt-Zollars JV | 22-035-000 | $5,129,039.00 | Amendment 7 | VIEW + |
| Michael Baker International and Huitt Zollar JV | 22-035-000 | $1,824,195.00 | Amendment 1 | VIEW + |
| Michael Baker International and Huitt-Zollars Joint Venture | 22-035-000 | $10,390,337.00 | Program Management Firm | VIEW + |
| Michael Baker International & Huitt-Zollars JV | 22-035-000 | $2,988,852.00 | Amendment 9 | VIEW + |
| Michael Baker International Huitt Zollars Joint Venture | 22-035-000 | $12,965,297.00 | Amendment 8 | VIEW + |
| Michael Baker International and Huitt-Zollars JV | 22-035-000 | ($1,444,056.00) | Amendment 11 | VIEW + |
| Michael Baker International and Huitt-Zollars JV | 22-035-000 | $7,374,296.00 | Amendment 10 | VIEW + |
| Inter-Con Security Systems Inc | 22-025-000 | $10,286,425.38 | Security Guard Services | VIEW + |
| Inter Con Security Systems Inc. | 22-025-000 | $0.00 | Amendment 2 | VIEW + |
| Inter Con Security Systems Inc | 22-025-000 | $0.00 | Amendment 1 | VIEW + |
| Jose I Guerra Inc | 22-015-000 | $400,000.00 | Amendment 1 | VIEW + |
| Jose I Guerra Inc | 22-015-000 | $400,000.00 | IDIQ MEP Services | VIEW + |
| Stanley Consultants Inc | 22-014-000 | $400,000.00 | IDIQ MEP Serivces | VIEW + |
| Stanley Consultants Inc | 22-014-000 | $222,800.00 | Assignment 1 | VIEW + |
| Stanley Consultants Inc | 22-014-000 | $86,800.00 | Assignment 2 | VIEW + |
| Stanley Consultants Inc | 22-014-000 | $0.00 | Amendment 1 to Assignment 1 | VIEW + |
| Stanley Consultants Inc | 22-014-000 | $400,000.00 | Amendment 1 | VIEW + |
| Stanley Consultants Inc | 22-014-000 | $0.00 | Amendment 1 to Assignment 2 | VIEW + |
| Stanley Consultants Inc | 22-014-000 | $90,400.00 | Assignment 3 | VIEW + |
| Stanley Consultants Inc | 22-014-000 | $82,581.00 | Assignment 6 | VIEW + |
| Stanley Consultants Inc | 22-014-000 | $91,500.00 | Assignment 7 | VIEW + |
| Stanley Consultants Inc | 22-014-000 | $727,414.00 | Amendment 2 | VIEW + |
| Stanley Consultants Inc | 22-014-000 | $113,800.00 | Assignment 4 | VIEW + |
| Stanley Consultants Inc | 22-014-000 | $86,200.00 | Assignment 5 | VIEW + |
| Stanley Consultants Inc | 22-014-000 | $727,414.00 | Amendment 1 to Assignment 7 | VIEW + |
| Stanley Consultants Inc | 22-014-000 | $0.00 | Amendment 1 to Assignment 5 | VIEW + |
| Stanley Consultants Inc | 22-014-000 | $90,400.00 | Amendment 1 to Assignment 3 | VIEW + |
| MEP Engineering Inc | 22-013-000 | $26,200.00 | Assignment 3 | VIEW + |
| MEP Engineering Inc | 22-013-000 | $25,000.00 | Assignment 4 | VIEW + |
| MEP Engineering Inc | 22-013-000 | $66,000.00 | Assignment 2 | VIEW + |
| MEP Engineering Inc | 22-013-000 | $69,800.00 | Assignment 1 | VIEW + |
| MEP Engineering Inc | 22-013-000 | $400,000.00 | Amendment 1 | VIEW + |
| MEP Engineering Inc | 22-013-000 | $400,000.00 | IDIQ MEP Services | VIEW + |
| Tom Green and Company Engineers Inc | 22-012-000 | $400,000.00 | IDIQ MEP Services | VIEW + |
| Tom Green and Company Engineers Inc | 22-012-000 | $400,000.00 | Amendment 1 | VIEW + |
| Tom Green and Company Engineers Inc | 22-012-000 | $43,000.00 | Assignment 3 | VIEW + |
| Tom Green and Company Engineers Inc | 22-012-000 | $80,000.00 | Assignment 1 | VIEW + |
| Tom Green and Company Engineers Inc | 22-012-000 | $100,000.00 | Assignment 2 | VIEW + |
| Tom Green and Company Engineers Inc | 22-012-000 | $0.00 | Amendment 1 to Assignment 2 | VIEW + |
| Tom Green and Company Engineers Inc | 22-012-000 | $177,000.00 | Assignment 4 | VIEW + |
| Tom Green and Company Engineers Inc | 22-012-000 | $0.00 | Cancelled Assignment 4 | VIEW + |
| Huitt-Zollars Inc | 22-011-000 | $0.00 | Amendment 1 to Assignment 3 | VIEW + |
| Huitt-Zollars, Inc | 22-011-000 | $30,510.00 | Assignment 3 | VIEW + |
| Huitt-Zollars Inc | 22-011-000 | $11,750.00 | Assignment 1 | VIEW + |
| Huitt-Zollars Inc | 22-011-000 | $17,275.00 | Assignment 2 | VIEW + |
| Huitt-Zollars Inc | 22-011-000 | $400,000.00 | Amendment 1 | VIEW + |
| Huitt Zollars | 22-011-000 | $400,000.00 | IDIQ MEP | VIEW + |
| Parkhill Smith & Cooper Inc dba Parkhill | 22-010-000 | $400,000.00 | IDIQ MEP | VIEW + |
| Parkhill Smith & Cooper Inc dba Parkhill | 22-010-000 | $88,995.00 | Assignment 1 | VIEW + |
| Parkhill Smith & Cooper Inc dba Parkhill | 22-010-000 | $65,000.00 | Assignment 3 | VIEW + |
| Parkhill Smith & Cooper Inc DBA Parkhill | 22-010-000 | $17,500.00 | Assignment 4 | VIEW + |
| Parkhill Smith & Cooper Inc dba Parkhill | 22-010-000 | $400,000.00 | Amendment 1 | VIEW + |
| Parkhill, Smith & Cooper Inc dba Parkhill | 22-010-000 | $168,500.00 | Assignment 2 | VIEW + |
| Parkhill Smith & Cooper Inc dba Parkhill | 22-010-000 | $0.00 | Amendment 1 to Assignment 1 | VIEW + |
| Parkhill Smith & Cooper Inc dba Parkhill | 22-010-000 | $6,279.00 | Amendment 2 to Assignment 1 | VIEW + |
| Parkhill Smith & Cooper Inc dba Parkhill | 22-010-000 | $83,500.00 | Assignment 8 | VIEW + |
| Parkhill Smith & Cooper Inc dba Parkhill | 22-010-000 | $230,000.00 | Assignment 9 | VIEW + |
| Parkhill Smith & Cooper Inc dba Parkhill | 22-010-000 | $200,000.00 | Amendment 2 | VIEW + |
| Parkhill Smith & Cooper Inc dba Parkhill | 22-010-000 | $19,825.00 | Assignment 6 | VIEW + |
| Parkhill Smith & Cooper Inc dba Parkhill | 22-010-000 | $113,850.00 | Amendment 1 to Assignment 2 | VIEW + |
| Parkhill Smith & Cooper Inc dba Parkhill | 22-010-000 | $117,500.00 | Assignment 7 | VIEW + |
| Parkhill Smith & Cooper Inc dba Parkhill | 22-010-000 | $28,500.00 | Assignment 5 | VIEW + |
| Parkhill, Smith & Cooper Inc dba Parkhill | 22-010-000 | $0.00 | Amendment 1 to Assignment 3 | VIEW + |
| Parkhill, Smith & Cooper Inc dba Parkhill | 22-010-000 | $0.00 | Amendment No. 2 to Assignment No. 2 | VIEW + |
| Garver LLC | 22-009-000 | $51,315.00 | Assignment 2 | VIEW + |
| Garver LLC | 22-009-000 | $21,353.00 | Assignment 3 | VIEW + |
| Garver LLC | 22-009-000 | $115,279.00 | Assignment 1 | VIEW + |
| Garver LLC | 22-009-000 | $400,000.00 | Amendment 1 | VIEW + |
| Garver LLC | 22-009-000 | $400,000.00 | IDIQ MEP Services | VIEW + |
| Freese and Nichols Inc | 22-008-000 | $400,000.00 | IDIQ MEP | VIEW + |
| Freese and Nichols Inc | 22-008-000 | $25,084.00 | Assignment 1 | VIEW + |
| Freese and Nichols Inc | 22-008-000 | $400,000.00 | Amendment 1 | VIEW + |
| Freese and Nichols Inc | 22-008-000 | $76,586.00 | Assignment 2 | VIEW + |
| Freese and Nichols Inc | 22-008-000 | $126,013.00 | Assignment 5 | VIEW + |
| Freese and Nichols Inc | 22-008-000 | $59,321.00 | Assignment 4 | VIEW + |
| Freese and Nichols Inc | 22-008-000 | $59,321.00 | Assignment 3 | VIEW + |
| Freese and Nichols Inc | 22-008-000 | $0.00 | Amendment 1 to Assignment 2 | VIEW + |
| Energy Engineering Associates Inc | 22-007-000 | $17,000.00 | Assignment No. 6 | VIEW + |
| Energy Engineering Associates Inc | 22-007-000 | $400,000.00 | Amendment 1 | VIEW + |
| Energy Engineering Associates Inc | 22-007-000 | $118,740.00 | Assignment 4 | VIEW + |
| Energy Engineering Associates Inc | 22-007-000 | $79,510.00 | Assignment 2 | VIEW + |
| Energy Engineering Associates Inc | 22-007-000 | $42,000.00 | Assignment 3 | VIEW + |
| Energy Engineering Associates Inc | 22-007-000 | $5,300.00 | Assignment 1 | VIEW + |
| Energy Engineering Associates Inc | 22-007-000 | $400,000.00 | IDIQ MEP | VIEW + |
| Affiliated Engineers Inc | 22-006-000 | $400,000.00 | IDIQ MEP Services | VIEW + |
| Affiliated Engineers Inc | 22-006-000 | $400,000.00 | Amendment 1 | VIEW + |
| Winstead PC | 22-005-000 | $0.00 | Amendment 3 | VIEW + |
| Winstead PC | 22-005-000 | $0.00 | Amendment 4 | VIEW + |
| Winstead PC | 22-005-000 | $250,000.00 | Outside Counsel Contract | VIEW + |
| Winstead PC | 22-005-000 | $0.00 | Amendment 1 | VIEW + |
| Winstead PC | 22-005-000 | $0.00 | Amendment 2 | VIEW + |
| Terracon Consultants Inc | 22-073-000 | $1,500.00 | Amendment No. 1 to Assignment No. 3 | VIEW + |